2026-11-10
Many agricultural, mining and remote water projects use a generator where grid power is unavailable. The main equipment is still the submersible well pump. The generator must be selected around the pump and motor.
At SLAPK, we begin with the water requirement and well conditions. After selecting the hydraulic pump, we confirm the motor, cable, starting method and generator requirements as one system.
Choosing a pump only because its motor matches an existing generator can result in insufficient flow, low pressure, motor overload or unstable starting.
Before discussing motor power, we confirm how much water the project needs and where it must be delivered.
The two main hydraulic values are:
Required flow rate
Total dynamic head
Total dynamic head is not the well depth. It includes lift from the pumping water level, discharge elevation, friction, fitting losses and required delivery pressure.
A pump installed 120 m below ground does not automatically need 120 m of head. The operating water level may be higher, while irrigation may require additional outlet pressure.
We select the pump from the point where the required flow and head occur together on the performance curve.
A suitable pump must fit the well and remain submerged during operation.
We ask for:
Total well depth
Minimum casing internal diameter
Static water level
Dynamic water level at a known flow
Well yield
Screen position
Sand content
Expected seasonal water-level change
If the dynamic level falls, the pump must lift water farther and flow may decrease as required head rises.
The pump should be installed below the lowest expected dynamic level with adequate submergence, but it should not be placed unnecessarily close to the well bottom or sediment zone.
Our QJ series is a multistage submersible well pump with cast hydraulic components. Different hydraulic models are designed for different flow ranges, while the number of stages is selected according to the required head.
We do not select a QJ pump from motor power or pump diameter alone. We compare:
Required flow and head
Casing diameter
Number of stages
Pump efficiency
Motor power
Water quality
Material requirements
Installation and maintenance conditions
The curve must pass through the duty within the approved range. Catalogue maximum flow and maximum head do not occur at the same point.
For clean, non-corrosive groundwater, a cast-iron QJ configuration may be suitable. Where water chemistry requires greater corrosion resistance, QJ pumps can be produced in stainless steel or other approved materials. Material selection should be based on water analysis rather than appearance or price alone.
The selected QJ pump outside diameter, cable guard, coupling and power cable must all fit through the minimum internal diameter of the well casing.
After hydraulic selection, we confirm absorbed power and choose the matching submersible motor.
The motor data should include:
Rated power
Rated current
Voltage
Frequency
Single-phase or three-phase supply
Number of leads
Starting method
Permitted voltage tolerance
An oversized motor does not correct a poor pump selection. An undersized motor may overload as water level or system resistance changes.
For generator-powered projects, the motor voltage and phase should be chosen only after confirming what the generator can supply reliably.
A submersible well pump motor requires more electrical power while starting than during normal running. A generator that can carry the running current may still fail to start the pump.
Possible symptoms include:
The motor does not accelerate
Generator speed falls sharply
Voltage collapses during startup
The contactor chatters
The overload relay trips
The pump starts only when other loads are disconnected
There is no single generator multiplier suitable for every well pump. We review the motor manufacturer's starting-current data and generator recommendations.
The generator supplier should confirm continuous and motor-starting capacity in kW and kVA. Peak power is not continuous output.
The starting method affects the generator, control panel and motor leads.
Direct starting is simple but normally produces the highest starting current. It may require a larger generator to keep voltage stable.
Star-delta starting can reduce starting current, but it also reduces starting torque. The motor winding and lead arrangement must support it.
A soft starter can reduce current and mechanical shock, but its ramp must provide enough torque without extending the start excessively.
A VFD can control acceleration and speed. The motor, minimum frequency, cooling, cable length and pump range must still be checked.
The generator must be sized for the VFD input characteristics. Installing a VFD does not automatically make every small generator suitable.
The cable route includes the surface section between the generator, panel and wellhead, plus the downhole cable.
An undersized cable causes voltage drop, which becomes greater during starting.
We size the cable from:
Motor rated current
Starting current
Supply voltage and phase
Complete cable length
Conductor material
Installation conditions
Permitted running and starting voltage drop
Increasing generator capacity does not solve excessive voltage drop in a thin, damaged or poorly connected cable.
The underwater splice must be secure, insulated and permanently water-tight.
The generator may be operating correctly while the submerged motor is still at risk from poor cooling.
The motor depends on water moving past its outer surface. We check:
Minimum operating water level
Water velocity around the motor
Well diameter
Pump position relative to the well screen
Water temperature
Need for a cooling sleeve
In a large well, tank or installation where water enters above the intake, a flow sleeve may be required.
Dry-running protection is essential where well yield may be lower than pump flow.
The control panel should match the selected motor and starting method.
Depending on the project, protection may include:
Short-circuit protection
Motor overload protection
Phase loss and phase sequence protection
Under-voltage and over-voltage protection
Current and voltage imbalance protection
Dry-running protection
Water-level control
Temperature monitoring
Protection settings should follow motor data rather than being increased to prevent nuisance trips.
During initial operation, we record:
Generator voltage before starting
Lowest voltage during motor acceleration
Running voltage and frequency
Current on every phase
Starting time
Flow rate
Discharge pressure
Dynamic water level
Vibration and abnormal noise
Compare these values with the pump curve, nameplate and approved operating point.
Incorrect phase sequence can reverse a three-phase pump. It may still deliver water with much lower flow and pressure, so rotation must be confirmed.
For a generator-powered well project, we work in this order:
Confirm the required water flow and delivery pressure.
Calculate total dynamic head.
Review the well yield, water levels and casing diameter.
Select the QJ pump from its performance curve.
Confirm motor power, voltage, frequency and current.
Select the starting method and control panel.
Calculate cable size and voltage drop.
Provide motor data for generator sizing.
Check cooling, submergence and dry-running protection.
Record the complete operating data during commissioning.
To select the pump, send:
Required flow and outlet pressure
Static and dynamic water levels
Well depth and casing internal diameter
Delivery elevation
Pipe diameter, length and fittings
Pump setting depth
Water analysis and sand content
Generator voltage, frequency, phase, kW and kVA ratings
Total cable length
Proposed starting method
Other loads connected to the generator
Daily operating hours
For a generator-powered well, the submersible pump should be selected from the real hydraulic duty and well conditions first. The motor, cable, starter, protection and generator must then be matched to that pump.
At SLAPK, we do not recommend a QJ well pump from motor kilowatts or generator size alone. We review the complete pumping system so the pump can start reliably and deliver the required water under actual operating conditions.
Send us your well data, required flow and head, cable length and generator information. We can prepare a suitable QJ submersible well pump recommendation for the project.
Contact SLAPK for a generator-powered QJ submersible well pump
Отправьте запрос непосредственно нам